Question

Seasons Construction is constructing an office building under contract for Cannon Cafe. The contract calls for progress billings and payment of $620,000 each quarter. The total contract price is $7,440,000 and Seasons estimates total costs of $7,100,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2010. At December 31, 2010, Season estimates that it is 30% complete with the construction, based on costs incurred. What is the total amount of Revenue from Long-term contracts recognized for 2010 and what is the balance in the Accounts Receivable account assuming Cannon Cafe has not yet made its last quarterly payment?
2,232,000/620,000
2,130,000/2,480,000
2,480,000/2,480,000
2,130,000/620,000

Explanation / Answer

2,130,000/620,000

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote