Percentage-of-Completion Method: Dalton Construction Co. contracted to build a b

ID: 2387156 • Letter: P

Question

Percentage-of-Completion Method:
Dalton Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2012 and was completed in 2013. Data relating to the construction are:
Costs incurred......................2012 - $3,300,000.....2011..............$2,750
Estimated costs to complete.....2012 - $2,700,000
A. How much revenue should be reported for 2012? Show your computations
B. Make the entry to record progress billings of $3,300,000 during 2012
C. Make the entry to record the revenue and gross profit for 2012
D. How much gross profit should be reported for 2013? Show your computations.

I need this by Saturday, February 4, 2012. Thank you.

Explanation / Answer

A. How much revenue should be reported for 2012?

=3,300,000 / 6,000,000      x 10,000,000=$5,500,000

=======================

B. Make the entry to record progress billings of $3,300,000 during 2012

Acounts receivable

3,300,000

Billing on construction process

3,300,000

=================

C. Make the entry to record the revenue and gross profit for 2012

construction expenses

3,300,000

construction in process

2,200,000

Revenue from long term contrac

5,500,000

============

D. How much gross profit should be reported for 2013? Show your computations.

Revenue

10,000,000

costs

6,050,000

Total gros profit

3,950,000

Recognised 2012

(2,200,000)

Recognised 2013

$ 1,750,000

Acounts receivable

3,300,000

Billing on construction process

3,300,000