Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

10-31 High-low method. Ken Howard, financial analyst at KMW Corporation, is exam

ID: 2388612 • Letter: 1

Question

10-31
High-low method. Ken Howard, financial analyst at KMW Corporation, is examining the behavior of quarterly maintenance costs for budgeting purposes. Howard collects the following data on machine hours worked and maintenance costs for the past 12 quarters:
Quarter Machine-Hours Maintenance Costs
1 1 00,000 $205,000
2 1 20,000 240,000
3 1 1 0,000 220,000
4 1 30,000 260,000
5 95,000 190,000
6 1 1 5,000 235,000
7 1 05,000 21 5,000
8 1 25,000 255,000
9 1 05,000 21 0,000
1 0 1 25,000 245,000
1 1 1 1 5,000 200,000
1 2 1 40,000 280,000
Required
1 . Estimate the cost function for the quarterly data using the high-low method.
2. Plot and comment on the estimated cost function.
3. Howard anticipates that KMW will operate machines for 1 00,000 hours in quarter 1 3. Calculate the redicted maintenance costs in quarter 1 3 using the cost function estimated in requirement 1 .

Explanation / Answer

Total Cost

Machine Hours

$280,000

140,000

$190,000

95,000

$90,000

45,000

VC per Machine Hour =$2

Total Cost

Total variable Cost

Total fixed Cost

$280,000

$280,000

$ 0 No fixed costs

$190,000

$190,000

$ 0 No fixed costs

Cost Function: Y = $2 (Machine Hours)


===============

Actual

Estimated

Machine

Maintenance

Maintenance

Quarter

Hours

ACosts

ECosts

1

100,000

$205,000

$200,000

2

120,000

$240,000

$240,000

3

110,000

$220,000

$220,000

4

130,000

$260,000

$260,000

5

95,000

$190,000

$190,000

6

115,000

$235,000

$230,000

7

105,000

$215,000

$210,000

8

125,000

$255,000

$250,000

9

105,000

$210,000

$210,000

10

125,000

$245,000

$250,000

11

115,000

$200,000

$230,000

12

140,000

$280,000

$280,000

.

The vertical differences between the actual and predicted costs appear to be quite small

=============

Estimated maintenance costs = 100,000 X $2 = $200,000

Total Cost

Machine Hours

$280,000

140,000

$190,000

95,000

$90,000

45,000

VC per Machine Hour =$2

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote