Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Sweeten Company had no jobs in progress at the beginning of March and no beginni

ID: 2394323 • Letter: S

Question

Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): 1,500 Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead per machine-hour 4,000 $14,250 $17,550 $31,800 2,500 3.10 3.90 Direct materials Direct labor cost Actual machine-hours used: Molding Fabrication Total $30,000 $16,500 $34,600 $14,300 3,400 2,500 2,3002,600 5,100 5,700 Sweeten Company had no underapplied or overapplied manufacturing overhead costs during the month. Required Forquestions?8, assume that Sweeten company uses a plantwide predetermined overhead rte with machine-hours as the allocation base. For questions 9-15, assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both departments . If Job Q included 30 units, what was its unit product cost? (Do not round intermediate calculations. Round your final answer to earest whole dollar.)

Explanation / Answer

Solution 6:

Plant wide pre determined overhead rate = Estimated overhead / Estimated machine hours

Estimated total overhead = Variable overhead + Fixed overhead = (2500*$3.10) + (1500*$3.90) + $31,800

= $45,400

Predetermined overhead rate = $45,400 / 4000 = $11.35 per machine hour

Solution 8:

Cost of goods sold for march = $129,295 + $88,685 = $217,980

Solution 9:

Solution 10:

Solution 11:

Note: I have answered more than required parts of the question as per chegg policy, kindly post separate question for answer of remaining parts.

Compuatation of unit product cost of Job Q Particulars Job Q Direct Material $16,500 Direct Labor $14,300 Manufacturing overhead
Q - 5100*$11.35 $57,885 Total Manufacturing cost $88,685 Nos of units $30 Unit product cost $2,956