Question 4(20 marks) financial controller of Zeta would like to replace its lega
ID: 2405664 • Letter: Q
Question
Question 4(20 marks) financial controller of Zeta would like to replace its legacy accounting system with an The enterprise resources planning (ERP), He is considering the possibility of outsourcing the ERP development project to contractors. Identify and explain Two (2) important issues that Zeta needs to tackle when managing the ERP contractor. (a) (8 marks) (b) ERP implementations will have significant impact on the accountants of Zeta. Suggest ANY THREE (3) things that the accountants in Zeta should do in order to prepare for the changes. (12 marks)Explanation / Answer
A. Two Important issue to tackle when managing ERP Contractors
While selecting the contractor, the business should come to an agreement on the timeline for completion of the ERP implementation.
The timeline should have the following milestones with the date of completion:
Sl No
Stage / Milestone
Completion Date
Understanding the business process
18 Jul 2019
Proto Type Understanding
18 Aug 2019
Customization of System
18 Sep 2019
GAP Analysis to Reduce the Risk
20 Oct 2019
Training to the Users
20 Nov 2019
User Acceptance Testing
20 Dec 2019
Data Migration from the old system
30 Dec 2019
GO live
01 Jan 2020
The management of the business should attach the timeline as an integral part of the agreement with the ERP contractor. In addition, the agreement should mention the penalties for the deviation from the agreed timeline.
2. History of the Contractor
The management of the company should consider the history of the previous implementations of the contractor before selecting the ERP contractor. For this, the officials of the company should visit the locations of the previously implemented businesses to understand the efficiency of the contractor.
B. Three Things The Accountant Should Do
Accountants should attend the training session to use the new system is one of the significant tasks while the implementing the ERP system. After the training, the Users (accountants) should sign the training manual to make sure that the training session was conducted in a sufficient manner.
2. Cleaning up of the data
The accountants should make sure that the data being migrated to the new system from the old system should be free from junks.
Examples;
3. Need identification
The accountants should identify the output they need from the newly implemented system. The output will mostly report they need to draw from the system. The accountants should give the report templates to the implementation team in advance so the reports will be available in the system for the day to day work.
Example: The receivable accountant needs the receivable aging report to calculate the credit limit and boost the payments from the customer to enhance the cash flow of the business.
Sl No
Stage / Milestone
Completion Date
Understanding the business process
18 Jul 2019
Proto Type Understanding
18 Aug 2019
Customization of System
18 Sep 2019
GAP Analysis to Reduce the Risk
20 Oct 2019
Training to the Users
20 Nov 2019
User Acceptance Testing
20 Dec 2019
Data Migration from the old system
30 Dec 2019
GO live
01 Jan 2020