Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Knickknack, Inc., manufactures two products: odds and ends. The firm uses a sing

ID: 2406573 • Letter: K

Question

Knickknack, Inc., manufactures two products: odds and ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows:

Knickknack, Inc., prices its products at 120 percent of cost, which yields target prices of $796.80 for odds and $1,195.20 for ends. Recently, however, Knickknack has been challenged in the market for ends by a European competitor, Bricabrac Corporation. A new entrant in this market, Bricabrac has been selling ends for $880 each. Knickknack’s president is puzzled by Bricabrac’s ability to sell ends at such a low cost. She has asked you (the controller) to look into the matter. You have decided that Knickknack’s traditional, volume-based product-costing system may be causing cost distortion between the firm’s two products. Ends are a high-volume, relatively simple product. Odds, on the other hand, are quite complex and exhibit a much lower volume. As a result, you have begun work on an activity-based costing system.

  

The plant has 3,840 square feet of space, 80 percent of which is used in the production of odds

Knickknack, Inc., manufactures two products: odds and ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows:

4 value: 1.43 points 2. For each activity cost pool, compute a pool rate. Activity Cost Pool Machine-related costs Setup and inspection Engineering Plant-related costs Pool Rate 100 per machine hour per run 1,800 per change order per square feet

Explanation / Answer

Activity

Cost Drivers

Total Activity Amount (A)

Level of Activity (B)

Activity Rate (C=A/B)

Machine Related Cost

Machine Houes

1800000

18000.00

$                      100.00

Per Machine Hour

Setup and Inspection

Number of Production Runs

720000

80.00

$                   9,000.00

Per Production Run

Engineering

Engineering Change Order

360000

200.00

$                   1,800.00

Per engineering change order

Pant Related Cost

Square Footage of space

384000

3840.00

$                      100.00

Per squarefoot

$   3,264,000.00

Overhead per unit

Odds

Activity rate(A)

Activity Driver Incurred (B)

Overhead Assigned (C=A*B)

Machine Related Cost

$                                     100.00

$           8,000.00

$        800,000.00

Setup and Inspection

$                                 9,000.00

40.00

$        360,000.00

Engineering

$                                 1,800.00

0.00

$                          -  

Pant Related Cost

$                                     100.00

3072.00

$        307,200.00

Total Overheads

$     1,467,200.00

Production

1000.00

Overhead cost per unit

$             1,467.20

Overhead per unit

Ends

Activity rate(A)

Activity Driver Incurred (B)

Overhead Assigned (C=A*B)

Machine Related Cost

$                                     100.00

$         10,000.00

$     1,000,000.00

Setup and Inspection

$                                 9,000.00

$                 40.00

$       360,000.00

Engineering

$                                 1,800.00

$               200.00

$        360,000.00

Pant Related Cost

$                                     100.00

$               768.00

$           76,800.00

Total Overheads

$     1,796,800.00

Production

5000.00

Overhead cost per unit

$                 359.36

statement of Total cost per unit

Odds

Ends

Direct Material

$                                     160.00

$               240.00

Direct Labour

$                                     120.00

$               180.00

Manufacturing Overheads

$                                 1,467.20

$               359.36

$                                 1,747.20

$               779.36

Calculation of New Target Prices

Odds

Ends

Total Cost

$                                 1,747.20

$               779.36

Profit (balancing figure)

$                                     349.44

$               155.87

Price (TOTALCOST*120%)

$                                 2,096.64

$               935.23

Statement showing assignment of total overhead cost

Manufacturing Overhead Cost Per Unit

Odds

Ends

Machine Related Cost

$                                     800.00

$               200.00

Setup and Inspection

$                                     360.00

$                 72.00

Engineering

$                                              -  

$                 72.00

Pant Related Cost

$                                     307.20

$                 15.36

Total Overhead Cost per unit

$                                 1,467.20

$               359.36

Production Units

1000

5000

Total Overhead Cost

$ 1467200

$ 1796800

$ 3264000

Cost Distortion

Odds

Ends

Total Cost as per Traditional Method

$                                     664.00

$               996.00

Total Cost as per ABC

$                                 1,467.20

$               359.36

$                                   (803.20)

$               636.64

Notes

Traditional method showed less cost in comparison to ABC in case of Odds

Traditional method showed high cost in comparison to ABC in case of ends.

Activity

Cost Drivers

Total Activity Amount (A)

Level of Activity (B)

Activity Rate (C=A/B)

Machine Related Cost

Machine Houes

1800000

18000.00

$                      100.00

Per Machine Hour

Setup and Inspection

Number of Production Runs

720000

80.00

$                   9,000.00

Per Production Run

Engineering

Engineering Change Order

360000

200.00

$                   1,800.00

Per engineering change order

Pant Related Cost

Square Footage of space

384000

3840.00

$                      100.00

Per squarefoot

$   3,264,000.00