Question

Direct Labor Budget

Evans Company produces asphalt roofing materials. The production budget in bundles for Evans' most popular weight of asphalt shingle is shown for the following months:

Each bundle produced requires (on average) 0.40 direct labor hours. The average cost of direct labor is $20 per hour.

A direct labor budget for March, April, and May, showing the hours needed and the direct labor cost for each month and in total. Do not include a multiplication symbol as part of your answer.

Units March 4,000 April 13,000 May 14,400 June 17,000

Explanation / Answer

Evans Company Direct labor budget

March

April

May

Total

Units to be produced

4000

13000

14400

31400

Direct labor time per unit (hours)

0.40

0.40

0.40

0.40

Total hours needed

1600

5200

5760

12560

Cost per hour

$20

$20

$20

$20

Total direct labor cost

$32000

$104000

$115200

$251200

Evans Company Direct labor budget

March

April

May

Total

Units to be produced

4000

13000

14400

31400

Direct labor time per unit (hours)

0.40

0.40

0.40

0.40

Total hours needed

1600

5200

5760

12560

Cost per hour

$20

$20

$20

$20

Total direct labor cost

$32000

$104000

$115200

$251200