Huang Aerospace Corporation manufactures aviation control panels in two departme
ID: 2412046 • Letter: H
Question
Huang Aerospace Corporation manufactures aviation control panels in two departments, Fabrication and Assembly. In the Fabrication department, Huang uses a predetermined overhead rate of $30 per machine-hour. In the Assembly department, Huang uses a predetermined overhead rate of $12 per direct labor-hour. During the current year, Job #X2984 incurred the following number of hours in each department:
Fabrication
Assembly
Machine hours...................
40
12
Direct labor hours..............
3
25
What is the total amount of manufacturing overhead that Huang should have applied to Job #X2984 during the current year?
$1,200
$1,500
$1,560
$1,734
Fabrication
Assembly
Machine hours...................
40
12
Direct labor hours..............
3
25
Explanation / Answer
b. $1,500
Job #X2984 Fabrication–overhead applied ($30 per machine-hour × 40 machine-hours) $1,200 Assembly–overhead applied ($12 per direct labor-hour × 25 direct labor-hours) $300 Total overhead applied to Job #X2984 $1,500Related Questions