The following data pertain to the Vesuvius Tile Company for July.Work in process
ID: 2412071 • Letter: T
Question
The following data pertain to the Vesuvius Tile Company for July.Work in process, July 1 (in units) .......................................................................................................................20,000Units started during July ...................................................................................................................................?Total units to account for ..................................................................................................................................65,000Units completed and transferred out during July ................................................................................................?Work in process, July 31 (in units) .....................................................................................................................15,000Total equivalent units: direct material .................................................................................................................65,000Total equivalent units: conversion ......................................................................................................................?Work in process, July 1: direct material .............................................................................................................$164,400Work in process, July 1: conversion ...................................................................................................................?Costs incurred during July: direct material .........................................................................................................?Costs incurred during July: conversion ..............................................................................................................659,400Work in process, July 1: total cost .....................................................................................................................244,200Total costs incurred during July .........................................................................................................................1,031,250Total costs to account for ..................................................................................................................................1,275,450Cost per equivalent unit: direct material .............................................................................................................8.25Cost per equivalent unit: conversion ..................................................................................................................?Total cost per equivalent unit ............................................................................................................................21.45Cost of goods completed and transfered out during July ......................................................................................?Cost remaining in ending work-in-process inventory: direct material ...................................................................?Cost remaining in ending work-in-process inventory: conversion .........................................................................79,200Total cost of July 31 work in process .................................................................................................................202,950Additional Information: a. Direct material is added at the beginning of the production process, and conversion activity occurs uniformly throughout the process. b. The company uses weighted-average process costing.
The July 1 work in process was 30 percent complete as to conversion. d. The July 31 work in process was 40 percent complete as to conversion. Required: Compute the missing amounts, and prepare the firm’s July production report.
Explanation / Answer
Solution:
Total units to be accounted for = 65000 units
Units in beginning WIP = 20000 units
Units started during period = 65000 - 20000 = 45000 units
Units in ending WIP = 15000 units
Units completed during period = 65000 - 15000 = 50000 units
Cost per equivalant unit - Direct material = $8.25
Total Cost per equivalant unit = $21.45
Cost per equivalant unit - conversion = $21.45 - $8.25 = $13.20
Total cost of direct material = 65000 * $8.25 = $536,250
Direct material cost in beginning WIP = $164,400
Direct material cost incurred during period = $536,250 - $164,400 = $371,850
Equivalant units of conversion = 50000 + 15000*40% = 56000 units
Total cost of conversion = 56000 * $13.20 = $739,200
conversion cost incurred during july = $659,400
Converstion cost from begining WIP = $739,200 - $659,400 = $79,800
Computation of Equivalent unit of Production - Weighted Average Particulars Physical Units Material Conversion Unit completed & Transferred out 50000 50000 50000 Closing WIP: 15000 Material (100%) 15000 Conversion (40%) 6000 Equivalent units of production 65000 65000 56000Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.