Leeds Architectural Consonants began operations on January 2 The following activity was recorded in the companys Work m Process account (or the NO month of operators Leeds Architectural Consultants is a service firm, so the names of the accounts it uses are different from the names used m manufacturing companies Costs of Subcontracted Work is comparable to Orect Materials Orect Staff Costs is the same as Direct Labor. Studio Overhead is the same as Manufacturing Overhead and Computed Projects is the same as Finished Goods Apart from the deference m terms, the accounting methods used by the company are identical to the methods used by manufacturing companiesExplanation / Answer
Leeds Architecture consultants Work In progress A/c
Cost of Substantial Products ( Direct Materials )
$ 90,000
To Completed Projects
$ 543,500
Direct Staff Costs ( Direct Labour)
$ 199,000
To Bal c/d
$ 44,000
Studio Overhead ( Overheads )
$ 298,500
Total
$ 587,500
Total
$ 587,500
Overheads are absorbed on the basis of Direct Staff costs
Overhead absorption Rate = Total Overheads/Direct staff costs
1.50
Predetermined overhead Rate
Cost Summary for one Job at end of January
Particulars
Amount
Direct Materials [ ( 44000 * 90000)/543500 ]]
$ 7,286
Direct Staff costs
$ 13,300
Overheads = Rate* Direct Staff costs
$ 19,950
Total Job cost
$ 40,536
Leeds Architecture consultants Work In progress A/c
Cost of Substantial Products ( Direct Materials )
$ 90,000
To Completed Projects
$ 543,500
Direct Staff Costs ( Direct Labour)
$ 199,000
To Bal c/d
$ 44,000
Studio Overhead ( Overheads )
$ 298,500
Total
$ 587,500
Total
$ 587,500
Overheads are absorbed on the basis of Direct Staff costs
Overhead absorption Rate = Total Overheads/Direct staff costs
1.50
Predetermined overhead Rate
Cost Summary for one Job at end of January
Particulars
Amount
Direct Materials [ ( 44000 * 90000)/543500 ]]
$ 7,286
Direct Staff costs
$ 13,300
Overheads = Rate* Direct Staff costs
$ 19,950
Total Job cost
$ 40,536