In Fulbright County, the Parks and Recreation Department constructed a library i
ID: 2416585 • Letter: I
Question
In Fulbright County, the Parks and Recreation Department constructed a library in one of the county’s high growth areas. The construction was funded by a number of sources. Below is selected information related to the Library Capital Project Fund. All activity related to the library construction occurred within the 2017 fiscal year.
Prepare a journal entry for capital projects fund and governmental activities at the government-wide level.(If no entry is required for a transaction/event, select "No Journal Entry Required" in the first account field.)
1. The county issued $7,900,000, 6 percent bonds, with interest payable semiannually on June 30 and December 31. The bonds solld for 101 on july 30, 2016. Proceeds from the bonds were to be used for construction of the library, with all interest and premiums received to be used to service the debt issue. Assume the premium and interest are recorded directly in the debt service fund.
Capital Project fund:
Government Activities:
2. A $840,000 federal grant was receive to help finance construction of the library.
Prepare a journal entry for capital projects fund and governmental activities at the government-wide level.(If no entry is required for a transaction/event, select "No Journal Entry Required" in the first account field.)
1. The county issued $7,900,000, 6 percent bonds, with interest payable semiannually on June 30 and December 31. The bonds solld for 101 on july 30, 2016. Proceeds from the bonds were to be used for construction of the library, with all interest and premiums received to be used to service the debt issue. Assume the premium and interest are recorded directly in the debt service fund.
Capital Project fund:
Government Activities:
3. The library special revenue fund transferred $440,000 for use in construction of the library.
Capital Project fund:
Government Activities:
4. A construction contract was awarded in the amount of $6,990,000
Capital Project fund:
Government Activities:
5. The library was completed on June 1, 2017, four months ahead of schedule. Total construction expenditures for the library amounted to $9,160,500. When the project was completed, the cost of the library was allocated as follows. $295,000 to land, $6,390,000 to building to building, and the remainder to equipment.
5a. Capital projects fund: Record the completion of construction of the library
5b. Capital projects fund: Record the payment upon completion of capital project.
5c. Govermenatal activities: Record the completion of construction of the library
5d Governmental activities: Record the capitalization of each item.
6. The capital projects fund temporary accounts were closed to fund balance-- restricted. The resources are restricted because they were obtained from bonded debt issued exclusively for library construction. The capital projects fund were closed by transferring remainin funds to the debt service fund for use in library construction debt repayment.
6a Capital Project fund: close the completion of construction of the library
6b Capital project fund: Record the transfer to the debt service fund.
6c Capital project fund: Close the remaining temporary account to Fund Balance- restricted.
6d. Governmental activities:
These are my options
No Journal Entry Required
Accumulated Depreciation
Appropriations
Bonds Payable
Budgetary Fund Balance
Buildings
Cash
Construction Expenditures
Construction Work in Progress
Encumbrances
Encumbrances Outstanding
Estimated Revenues
Expenditures
Expenses—General Government
Expenses—Public Safety
Fund Balance—Assigned
Fund Balance—Restricted
Fund Balance—Unassigned
Gain on Sale of Machinery
Interest Expenditures
Interest Payable
Interfund Transfers Out
Land
Loss on Sale of Machinery
Machinery and Equipment
Other Financing Sources—Interfund Transfers In
Other Financing Sources—Proceeds of Bonds
Other Financing Uses
Premium on Bonds Payable
Proceeds of Bonds
Program Revenues—Culture and Recreation—Capital Grants and Contributions
Program Revenues—Public Safety
Revenues
Vouchers Payable
In Fulbright County, the Parks and Recreation Department constructed a library in one of the county’s high growth areas. The construction was funded by a number of sources. Below is selected information related to the Library Capital Project Fund. All activity related to the library construction occurred within the 2017 fiscal year.
Explanation / Answer
Journal entry for capital projects fund and governmental activities at the government-wide level
Capital projects fund Government activities
1. Cash $7,900,000 1. Cash $7,900,000
To Other financing sources $7,900,000 To Bonds payable $7,900,000
(being proceeds of bonds) (being proceeds of bonds)
3 Cash $440,000
To Other Financing Sources-Interfund Transfers in $440,000 No journal entry needed
(being cash transfered for construction of library)
Construction expenditures Infrastucture assets $9,160,500
Land $295,000 To Cash $9,160,500
Building $6,390,000
Equipment $2,475,500
To Cash $9160500
(being completion of work and payment of amount)