Tamar Co. manufactures a single product in one department. All direct materials

ID: 2417496 • Letter: T

Question

Tamar Co. manufactures a single product in one department. All direct materials are added at the beginning of the manufacturing process. Conversion costs are added evenly throughout the process. During May, the company completed and transferred 22,200 units of product to finished goods inventory. Its 3,000 units of beginning work in process consisted of $19,800 of direct materials and $221,940 of conversion costs. It has 2,400 units (100% complete with respect to direct materials and 80% complete with respect to conversion) in process at month-end. During the month, $496,800 of direct material costs and $2,165,940 of conversion costs were charged to production.

Prepare the company’s process cost summary for May using the weighted-average method

Explanation / Answer

                                                          Materials                          Conversion

Transferred                                      22,200                               22,200

Ending WIP                                        2,400                                 1,920

total equivalent units                      24,600                               24,120

Beginning WIP cost                         19,800                            221,940

Added during the year                  496,800                          2,165,940

total cost                                        516,600                          2,387,880

Cost per unit                                      $21                                $99

cost Summary

Beginning WIP                                  $241,740

Added during the year                  2,662,740

total costs                                    $2,904,480

cost accounted for

Transferred out                              2,664,000

Ending WIP                                         240,480

total cost                                        $2,904,480