Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

In regards to calculating C. of this question. How do you determine $460,000 as

ID: 2417788 • Letter: I

Question

In regards to calculating C. of this question. How do you determine $460,000 as the total activity cost? the sum of $146k, $60k, $90k, $56k and $96k is $448,000 and I'm a little confused on how $460,00 was determined.

Calculating Activity-Based Costing Overhead Rates

Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs:

The following additional data were provided for Job 845:

3 change orders


(a) Calculate the cost per unit of activity driver for each activity cost category.

(b) Calculate the cost of Job 845 using ABC to assign the overhead costs.

(c) Calculate the cost of Job 845 using the plantwide overhead rate based on machine hours. (Round your answer to the nearest dollar.)

Setup (1,000 setup hours) $ 146,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 90,000 Supervision (2,000 direct labor hours) 56,000 Machine maintenance (12,000 machine hours) 96,000 Total activity costs $ 448,000

Explanation / Answer

a) Cost per unit of activity driver for each activity cost category -

Setup = $146000 / 1000 = $146

Production scheduling = $60000 / 400 = $150

Production engineering = $90000 / 60 = $1500

Supervision = $56000 / 2000 = $28

Machine maintenance = $96000 / 12000 = $8

b) Cost of Job 845 using ABC -

Particulars                                                                                                                       Amt   

Direct Material cost                                                                                                             $8000

Direct Labour cost                                                                                                               $1000

Setup ($146 * 5 hrs)                                                                                                           $730

Production scheduling ($150 * 1 batch)                                                                                  $150

Machine maintenance ($8 * 30 hrs)                                                                                       $240

Production engineering ($1500 * 3 change orders)                                                                 $4500   

Total cost                                                                                                                         $14620

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote