Ultra Manufacturing produces wooden chairs. The cutting department produces all
ID: 2419579 • Letter: U
Question
Ultra Manufacturing produces wooden chairs. The cutting department produces all of the component parts and transfers the parts to the assembly department. The assembly department had no work in process at the beginning of the month and had two jobs started during the month. Since materials are transferred in, all materials are charged to each job at the beginning of the job. The materials cost is $17.50 per chair. Assembly time is 20 minutes per chair and the direct labor rate is $15 per hour. Overhead is charged to a job only when a job is completed and ready to transfer to finished goods. The overhead is applied on a per-chair basis at a rate of $6 per chair. Job No. 1 was for 1,000 chairs, and it was started and completed during the month. Job No. 2 was for 1,500 chairs, and it was 60% complete at month end.
Calculate the costs to complete Job No. 1 and the unit cost per chair. Calculate the costs charged as of month's end and the equivalent units of production for Job No. 2.
Explanation / Answer
1./ JOB NO 1
2./ JOB NO 2
PARTICULLAR AMOUNT $ MATERIAL COST (1000 * $17.5) 17500 LABOUR COST OF ASSEMBLY [(1000 * 20) / 60] * $15 5000 OVERHEAD (1000 * $6) 6000 COST OF 1000 CHAIRS 28500 COST PER UNIT ($28500 /1000) 28.5Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.