The following data was input into a spreadsheet program to determine the Interce
ID: 2420613 • Letter: T
Question
The following data was input into a spreadsheet program to determine the Intercept, Slope and R2 (RSQ) for Patient Days and Maintenance Costs for a local hospital: Month Patent Days (X) Maintenance Costs (Y) January 6,600 $8,900 February 8,100 $9,500 March 6,000 $8,400 April 7,500 $9,200 May 8,300 $10,100 June 9,000 $10,800 July 5,200 $8,800 Intercept $5,468 Slope $0.541 RSQ 0.79
The estimated total maintenance cost for August based on an estimated 7,000 patient days is:
$9,255
$7,186
$7,985
$7,529
Explanation / Answer
Cost Function as per given slope and intercept will be:
Y = 5468+0.541X
For 7000 patient days
Y = 5468+0.541(7000)
Y = 5468+3787
Y = 9255 or Maintenance Cost is $9,255