Logan, Inc., had 9,000 units of work in process in Department M on March 1 that
ID: 2422808 • Letter: L
Question
Logan, Inc., had 9,000 units of work in process in Department M on March 1 that were 50 percent complete as to conversion costs. Materials are introduced at the beginning of the process. During March, 18,000 units were started, 20,000 units were completed, and there were 1,000 units of normal losses. Logan had 6,000 units of work in process at March 31 that were 60 percent complete as to conversion costs. Under Logan's cost accounting system, lost units reduce the number of units over which total cost can be spread. Using the average cost method, what were the equivalent units for March for conversion costs?
Explanation / Answer
Calculation of equivalent units for March for conversion costs:
(Using the average cost method)
Units in beginning Work in Process
9000
Units started during March
18000
Units Completed in March
20000
Units started and Completed in March (20000-9000)
11000
Units in ending work in process = 6000 * 60% =
3600
Equivalent units for March for conversion costs = (11000+3600)
14600
Calculation of equivalent units for March for conversion costs:
(Using the average cost method)
Units in beginning Work in Process
9000
Units started during March
18000
Units Completed in March
20000
Units started and Completed in March (20000-9000)
11000
Units in ending work in process = 6000 * 60% =
3600
Equivalent units for March for conversion costs = (11000+3600)
14600
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.