Nova company\'s total overhead cost at various levels of activity are presented
ID: 2423399 • Letter: N
Question
Nova company's total overhead cost at various levels of activity are presented below: Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Nova company's management wants to break down the maintenance cost into its variable and fixed cost elements: Required: Estimate how much of the $274,530 of overhead cost in july was maintenance cost (Do not round intermediate calculations.)Explanation / Answer
Utilities cost per hour = $57,400/41,000 hours = $1.40 per hour
Highest level of machine hours = 71,000 and lowest level = 41,000
Thus maintenace cost in July = 274,530 - 99,400-69,000
= $106,130
41000 Mhs 71000 Mhs Total overhead cost 195,630.00 274,530.00 less: Utilities cost@ 1.4 per hr 57,400.00 99,400.00 Supervisors salary 69,000.00 69,000.00 Maintenance cost (balancing figure) 69,230.00 106,130.00Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.