Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

On March 1, 2014, Pechstein Construction Company contracted to construct a facto

ID: 2424437 • Letter: O

Question

On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,091,000. The building was completed by October 31, 2016. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2014, 2015, and 2016 are given below. 2014 2015 2016 Contract costs incurred during the year $2,773,930 $2,882,630 $1,987,440 Estimated costs to complete the contract at 12/31 3,677,070 1,987,440 –0– Billings to Fabrik during the year 3,486,000 3,484,000 1,121,000 (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) 2014 $ $ % $ $ 2015 $ $ % $ $ 2016 $ $ (b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. 2014 $ 2015 $ 2016 $ Click if you would like to Show Work for thi

Explanation / Answer

Ans:

(a)                                                Computation of Recognizable Profit/Loss

                                                           Percentage-of-Completion Method

           

2010

          Costs to date (12/31/10)......................................................................                              $2,880,000

          Estimated costs to complete...............................................................                              3,520,000

                    Estimated total costs.................................................................                              $6,400,000

          Percent complete ($2,880,000 ÷ $6,400,000)....................................                                        45%

          Revenue recognized ($8,400,000 X 45%).........................................                              $3,780,000

          Costs incurred....................................................................................                              2,880,000

          Profit recognized in 2010...................................................................                              $   900,000

2011

          Costs to date (12/31/11)

              ($2,880,000 + $2,230,000)..............................................................                              $5,110,000

          Estimated costs to complete...............................................................                              2,190,000

                    Estimated total costs.................................................................                              $7,300,000

          Percent complete ($5,110,000 ÷ $7,300,000)....................................                                        70%

          Revenue recognized in 2011..     ($8,400,000 X 70%) – $3,780,000                             $2,100,000 Costs incurred in 2011...........................................................................................                              2,230,000

          Loss recognized in 2011.....................................................................                              $ (130,000)

                                                                                       

2012

          Total revenue recognized..................................................................                              $8,400,000

          Total costs incurred...........................................................................                              7,300,000

          Total profit on contract.....................................................................                                1,100,000

          Deduct profit previously recognized

              ($900,000 – $130,000).....................................................................                                   770,000

          Profit recognized in 2012...................................................................                             $   330,000*

*Alternative

          Revenue recognized in 2012

              ($8,400,000 X 30%)........................................................................                               $2,520,000

          Costs incurred in 2012.......................................................................                               2,190,000

          Profit recognized in 2012...................................................................                               $   330,000

(b)                                                Computation of Recognizable Profit/Loss

                                                               Completed-Contract Method

          2010—NONE

          2011—NONE

2012

          Total revenue recognized..................................................................                               $8,400,000

          Total costs incurred...........................................................................                               7,300,000

          Profit recognized in 2012...................................................................                               $1,100,000

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote