X Company wants to estimate overhead costs in March, when production is expected
ID: 2424766 • Letter: X
Question
X Company wants to estimate overhead costs in March, when production is expected to be 1,400 units. It used account analysis with the January cost information below to determine the parameters of the cost function. January production was 1,000 units.
Total
Total Variable
Utilities
$40,100
$40,100
Maintenance
53,000
27,560
Supervision
23,000
0
What is X Company's estimate of total overhead costs in March [round intermediate unit costs to the nearest cent]?
Total
Total Variable
Utilities
$40,100
$40,100
Maintenance
53,000
27,560
Supervision
23,000
0
Explanation / Answer
When productio is 1400 units
Total total variable utilities 56140 56140 maintenance 64024 38584 supervision 2300 0Related Questions