Madtack Company uses a job-order costing system and started the month of March w
ID: 2430298 • Letter: M
Question
Madtack Company uses a job-order costing system and started the month of March with only one job in process (Job #359). This job had $5,000 of total cost assigned to it at the beginning of March. Madtack applies overhead to jobs at a rate of 175% of direct labor cost. During March, Madtack assigned production costs as follows to the jobs worked on during the month: Job #359 Job #360 Job #361 direct materials .......... $1,000 $5,000 $3,000 direct labor .............. 2,000 3,000 2,000 During March, Madtack completed and sold Job #360. Job #361 was also completed but was not sold by the end of March. Job #359 was not completed by the end of March. Madtack Company had total actual overhead cost of $10,700 for the month of March. Calculate Madtack's cost of goods manufactured for March.
Explanation / Answer
Job Cost sheet Job 359 Job 360 Job 361 Total Beginning Inventoty of WIP 5000 5000 Add: Material 1000 5000 3000 9000 Add: Labour 2000 3000 2000 7000 Add: Overheads applied @175% of DLC 3500 5250 3500 12250 Total Cost 11500 13250 8500 33250 Status WIP Sold FG Schedule showing Cost of Goods manufactured Beginning Inventory of WIP 5000 Add: Current cost of Manufacture: Material added in Jobs 9000 Labour added in Jobs 7000 Overheads applied (175% of 7000) 12250 Total Current cost of manufacturing 28250 Cost of Goods manufacturing 33250 Less:Ending inventory of WIP 11500 Cost of Goods manufactured (Job No. 360/361) 21750
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.