Compute the net present value of the project. (Negative amount should be indicat

ID: 2430660 • Letter: C

Question

Compute the net present value of the project. (Negative amount should be indicated by a minus sign. Round discount factor(s) to 3 decimal places, intermediate and final answers to the nearest dollar amount.)

Net present value=

Information needed:

PV of $1 - http://lectures.mhhe.com/connect/0078025419/Exhibit/Exhibit%2011B-1.JPG

PVA of $1 - http://lectures.mhhe.com/connect/0078025419/Exhibit/Exhibit%2011B-2.JPG

** please use numbers exactly from the tables.

Juliar Inc. has provided the following data concerning a proposed investment project: (Ignore income taxes.)

Explanation / Answer

Net present value = PV of cash inflows + PV of salvage value - Initial Outlay

NPV = ($54,000 x 7.139) + ($44,000 x 0.429) - $370,000

NPV = $385,506 + $18,876 - $370,000 = $34,382

PVIFA of (8%, 11) is 7.139

PVIF of (8%, 11) = 0.429

"It would be appreciated if you give your feedback"

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote