1. LMN Ltd has the following datarelating to its assembly plant for the year to 31 March Year 7:
£
Material costs
1,000,000
Direct labour costs
500,000
Assembly plant indirect costs
200,000
Inaddition, the stores departments has total costs of£60,000, and spends 50% of its time servicing the assemblyplant. In Year 7, there were 100,000 labour hours worked and 50,000machine hours run in the assembly plant. What was the overhead costper direct labor hour?
£
Material costs
1,000,000
Direct labour costs
500,000
Assembly plant indirect costs
200,000
Explanation / Answer
(£200,000 + £30,000)/(100,000 labour hours) = £2.30 per hour. Answer: £2.30 per hour.