standard quantity per unit of output..... 6.8 meters standard price......... $14
ID: 2433533 • Letter: S
Question
standard quantity per unit of output..... 6.8 meters standard price......... $14.40The following data pertains to operations concerning theproduct for the last month: Actual material purchased...... 4,400 meters Actual cost of material purchased.... $60,500 Actual material used in production ... 3,800 meters Actual output... 400 units
What is the materials price variance for the month?
standard price......... $14.40
The following data pertains to operations concerning theproduct for the last month: Actual material purchased...... 4,400 meters Actual cost of material purchased.... $60,500 Actual material used in production ... 3,800 meters Actual output... 400 units
What is the materials price variance for the month?
Explanation / Answer
Materials PriceVariance = ( Actual Price- Standard Price ) x Actual Quantity = ($13.75 - 14.40 ) x 3,800 meters = $2470FavorableRelated Questions