15. Zanny Electronics Companyuses a standard cost system to collect costs relate
ID: 2433641 • Letter: 1
Question
15. Zanny Electronics Companyuses a standard cost system to collect costs related to theproduction of its water ski radios. The direct labor standard foreach radio is 0.9 hours. The standard direct labor cost per hour is$7.20.
During the month of August, Zanny's water ski radio production used6,600 direct labor-hours at a total direct labor cost of $48,708.This resulted in production of 6,900 water ski radios for August.What is Zanny's labor rate variance for the month of August?
A) $972 favorable
B) $1,188 unfavorable
C) $2,160 favorable
D) $2,808 unfavorable
E) None of the above
16. Information on WestcottCompany's direct labor costs for a recent month follows:
Standard direct labor rate..........................
$3.75
Actual direct labor rate..............................
$3.50
Total standard direct labor-hours..............
10,000
Direct labor efficiency variance................
$4,200
Unfavorable
What were the actual hours worked during the month, rounded to thenearest hour?
A) 10,714
B) 11,120
C) 11,200
D) 11,914
E) None of the above
Standard direct labor rate..........................
$3.75
Actual direct labor rate..............................
$3.50
Total standard direct labor-hours..............
10,000
Direct labor efficiency variance................
$4,200
Unfavorable
Explanation / Answer
Standard direct labor rate..........................
$3.75
Actual direct labor rate..............................
$3.50
Total standard direct labor-hours..............
10,000
Direct labor efficiency variance................
$4,200
Unfavorable
What were the actual hours worked during the month, rounded to thenearest hour?
B) 11,120
Standard direct labor rate..........................
$3.75
Actual direct labor rate..............................
$3.50
Total standard direct labor-hours..............
10,000
Direct labor efficiency variance................
$4,200
Unfavorable