(Question 1) (Question 2) The actual and standard direct materials costs for pro
ID: 2437823 • Letter: #
Question
(Question 1)
(Question 2)
The actual and standard direct materials costs for producing a specified quantity of product are as follows 51,000 lbs. at $5.05 50,000 lbs. at $5.00 $257,550 $250,000 Actual Standard The direct materials price variance is: O $50 unfavorable O $2,500 unfavorable O $2,550 unfavorable $7,550 unfavorable Question 8 2 pts Using the information in Question #7 above, the direct materials quantity variance is: O $5,000 unfavorable $5,050 unfavorable $5,000 favorable O $5,050 favorableExplanation / Answer
Question 1
Direct materials price variance = (Actual price – Standard price) × Actual quantity
= (5.05 - 5) * 51,000
= 2,550 Unfavourable
Question 8
Direct materials quantity variance = (Actual quantity – Standard quantity) ×Standard price
= (51,000 - 50,000) * 5
= 5,000 Unfavourable
Question 2
Direct labor rate variance = (Actual rate per hour – Standard rate per hour) ×Actual direct labour hours
= (11.8 - 11) * 4,500
= 3,600 Unfavourable.
Question 10
Direct labor time variance = (Actual direct labor hours – Standard direct labor hours) × Standard rate per hour
= (4,500 - 4,800) * 11
= 3,300 favourable.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.