The company acquired an adjacent lot to construct a new warehouse, paying $30,00
ID: 2443504 • Letter: T
Question
The company acquired an adjacent lot to construct a new warehouse, paying $30,000 and giving a short term note for $270,000. Legal fees of $1,425 were paid. Delinquent taxes assumed were $12,000, and fees paid to remove an old bldg from the land came to $18,500.On top of all that, Materials salvaged from the demolition of said bldg were sold for $4,500, and a contractor was paid $910,000 to construct the new warehouse.
So trying to determine the actual cost of the land to be reported is where I am getting stuck. Help would be greatly appreciated.
Explanation / Answer
Calculating the total cost of the land: Cash $30,000 Short-term notes $270,000 Legal fees $1,425 Delinquent taxes $12,000 Removal costs $18,500 ----------------------------------- Sub total $331,925 (-) Salvaged materials $4,500 ----------------------------------- Total cost of land $327,425 ---------------------------------- Therefore, the total cost of land is $327,425.Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.