Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Your division is considering two investment projects, each of which requires an

ID: 2445158 • Letter: Y

Question

Your division is considering two investment projects, each of which requires an

up-front expenditure of $25 million. You estimate that the cost of capital is 10% and

that the investments will produce the following after-tax cash flows (in millions of

dollars):

Year Project A Project B

1 520

2 10 10

3 15 8

4 20 6

a. What is the regular payback period for each of the projects?

b. What is the discounted payback period for each of the projects?

c. If the two projects are independent and the cost of capital is 10%, which project or

projects should the firm undertake?

d. If the two projects are mutually exclusive and the cost of capital is 5%, which project

should the firm undertake?

e. If the two projects are mutually exclusive and the cost of capital is 15%, which project

should the firm undertake?

f. What is the crossover rate?

g. If the cost of capital is 10%, what is the modified IRR (MIRR) of each project?

Explanation / Answer

computation of Payback period

Years Project A Cumulative cash flows Project B Cumulative cash flows

1 5 5 20 20

2 10 15 10 30

3 15 30 8 38

4 20 50 6 44

project A : payback perid = 2 + 10 / 15

= 2 + 0.67 = 2.67

Project B : payback period = 1+ 5 /10 = 1.5

b. Computation of Discounted payback period

Years Project A discount @10% PVCF Cummulative CF Project B PVCF Cumulative CF

1 5 0.909 4.55 4.55 20 18.18 18.18

2 10 0.826 8.26 12.81 10 8.26 26.44

3 15 0.751 11.27 24.08 8 6.01 32.45

4 20 0.683 13.66 37.74 6 4.09 36.54

Discounted pay back period:

Project A = 3 + (0.92 / 13.66) = 3.07

project B = 1 + (6.82 / 8.26) = 1.83

c. Computation of Net present value

Years Project A Discount@10% Present value cash flows Project B Present value of cash flows

1 5 0.909 4.55 20 18.18

2 10 0.826 8.26 10 8.26

3 15 0.751 11.27 8 6.01

4 20 0.683 13.66 6 4.09

Total cash inflows 37.74 36.54

less : initial investment (25) (25)

NPV 12.74 11.54

Project A is better NPV . so you can choose Poject A

d.  Computation of NPV

Years Project A Discount@5% PVCF Project B PVCF

1 5 0.952 4.76 20 19.04

2 10 0.907 9.07 10 9.07

3 15 0.864 12.96 8 6.91

4 20 0.823 16.46 6 4.94

total cash inflows 43.25 39.96

less : initial investment (25) (25)

Npv 18.25 14.96

Project A i s better NPV . So you can choose Project A.

e. Computation of NPV

Years Project A Discount@15% PVCF Project B PVCF

1 5 0.869 4.35 20 17.38

2 10 0.756 7.56 10 7.56

3 15 0.658 9.87 8 5.26

4 20 0.572 11.44 6 3.43

Total cash inflows 33.22 33.63

less: initial invetment (25) (25)

NPV 8.22 8.63

Project B has more NPV than compare to the Project A . S you can choose anyone.

g. Based upon above table like c. and d. compute IRR

IRR = lower rate + ( lower rate NPV / lower rate NPV - higher rate NPV) * difference factor

project A :

IRR = 5+ (18.25 / 18.25 - 12.74) * 5 = 22%

Project B :

IRR = 5 + (14.96 / 14.96 - 11.54) * 5 = 27%.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote