Harrys Sandwich Shop makes great deli sandwiches. Harry employs 3 workers in addition to himself. Allen takes orders and prepares the bread. Barry builds the sandwich with meats and vegetables. Charlie prepares the drink and adds pickles, chips and wraps the sandwich. Finally, Harry operates the cash register. The average cycle time for each activity is show in the table below. What is the overall capacity of this process? task cycle time (sec) take order 20 prepare bread 15 build sandwich 35 prepare drink 10 add pickles,chips and wrap 20 collect money and finish check out 30
Explanation / Answer
What is overall capacity of this process?
The average cycle time for each activity is show in the table below.
Task cycle time in sec
Total 130 sec convert in minutes 2 Min 16 sec is required overall process.
Now process divided in 4 below persons as per illustration,
Allen- Order and prepares bread - 20+15=35 sec
Barry – builds the sandwich with meats - 35 sec
Charlie- prepared drink and pickles chips and wrap - 20 sec
Harry – Handled cash counter - 30 sec