Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Oro Mining , Inc., has just discovered 2 new mining sites for copper. Geologists

ID: 2448421 • Letter: O

Question

Oro Mining , Inc., has just discovered 2 new mining sites for copper. Geologists and engineers have come up with the following estimates regarding the costs and copper yeilds if the mines are opened:

Total tons of copper that can be extracted over the life time of the mine

Oro's owners currently demand a return of 18% of the market price of copper.

Instructions:

a. If the current market price of copper is $10 per ton, what is Oro's target cost per ton?

b. Given the $10 market price, should either of the mines be opened? and why?

c. The engineer working on site Z believes that if a customer convey system is installed, the variable extraction cost could be reduced to $3.50 per ton. The purchase price of the system is $20,000, but the costs to restore the site will increase to $30,000 if it is installed. Given the current $10 market price, should Oro install th conveyor and open site Z?

Site A Site Z Variable extraction costs per ton $4.20 $4.50 Fixed costs over the life of the mine: Blasting $160,000 $200,000 Construction $240,000 $260,000 Maintenance $30,000 $30,000 Restoration costs $50,000 $10,000 Total fixed costs $480,000 $500,000

Total tons of copper that can be extracted over the life time of the mine

$240,000 $200,000

Explanation / Answer

Answer :

a) the target cost per ton of copper = Price per ton of copper - target return

= 10 - (10*0.18)

= 10- 1.8

= 8.2

b) Return from Mine A = expected revenue - variable cost - fixed costs

= 240000(10-4.2) - 480000

= 912000

percentage return = 912000/240000

=3.8

Return from Mine Z = 200000(10-4.5) - 500000

=600000

per ton return from mine Z =600000/200000

=3

Since the return per tonn is higher than required in case of both mines thus both can be opened but Mine A has higher return.

Answer c) Revised fixed cost for mine Z

= 500000+20000+20000

= 540000

Return from site Z = 200000(10-3.5) - 540000

= 1300000-540000

=760000

return per ton = 760000/200000

= 3.8

Now the return of site Z is equal to site A and both of them can be opened

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote