Krizum Industries makes heavy construction equipment. The standard for a particu
ID: 2450982 • Letter: K
Question
Krizum Industries makes heavy construction equipment. The standard for a particular crane calls for 31 direct labor-hours at $15 per direct labor-hour. During a recent period 1,850 cranes were made. The labor rate variance was zero and the labor efficiency variance was $6,300 unfavorable. How many actual direct labor-hours were worked?
A) 63,650
B) 57,350
C) 57,770
D) 55,500
Krizum Industries makes heavy construction equipment. The standard for a particular crane calls for 31 direct labor-hours at $15 per direct labor-hour. During a recent period 1,850 cranes were made. The labor rate variance was zero and the labor efficiency variance was $6,300 unfavorable. How many actual direct labor-hours were worked?
Explanation / Answer
Answer:
Correct Answer is (C) 57,770 Hours
Here is working and calculation
Standard Direct Labour Hours for a crane = 31 Hours
Standard Rate per Direct Labour Hour = $15 per hour
Actual Cranes made during the period = 1,850 Cranes
Standard Direct Labour Hours for Actual Output = 1,850 Cranes x 31 Hours per Crate = 57,350 Hours
Labour Efficiency Variance = Standard Rate x (Standard Hours for Actual Output – Actual Hours) = -$6,300
-$6,300 = $15 (57,350 – Actual Hours)
-$6,300 = $860,250 – Actual Hours x $15
Actual Hours = ($860,250 + $6,300) / $15 = 57,770 Hours
Actual Direct Labour Hours worked = 57,770 Hours