Refer to Brennan Company. What is the material price variance (calculated at poi
ID: 2451060 • Letter: R
Question
Refer to Brennan Company. What is the material price variance (calculated at point of purchase)?
Hide FeedbackShow All Feedback
Check My Work Feedback
Post Submission Feedback
Solution
Brennan CompanyThe following information is for Brennan Company's September production:
Standards: Material 4.0 feet per unit @ $3.75 per foot Labor 3.0 hours per unit @ $8.25 per hour Actual: Production 3,500 units produced during the month Material 14,200 feet used; 14,700 feet purchased @ $3.70 per foot Labor 10,400 direct labor hours @ $8.35 per hour
(Round all answers to the nearest dollar.)
Explanation / Answer
Material price variance = ( Actual price - Standard price ) x Actual quantity used
= ( $3.70- $ 4.00 ) x 14,200 feet used
= $0.30 x 14,200
= $4260-F-favourable since actual price is less than standard price.
None of the options given is correct.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.