Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

(CPA) Jackson Inc. is preparing a budget for the coming year and requires the co

ID: 2452077 • Letter: #

Question

(CPA) Jackson Inc. is preparing a budget for the coming year and

requires the cost of steam used in its plant to be divided into its fixed and variable elements. The following data on the cost of steam used and direct manufacturing labor-hours (DMLH) used are available for the last six months:

                       

                        Cost of

Month              Steam                      DMLH

July                 $ 15,850                     3,000

August                 13,400                     2,050

September          16,370                     2,900

October               19,800                     3,650

November           17,600                     2,670

December           18,500                     2,650

Total                $101,520                     16,920

1.Assuming Jackson uses the high-low method, the estimated variable cost of steam per DMLH is:                                                    $___________

2.Using the information in question 1 and assuming Jackson uses the high-low method, the estimated amount of the constant is:     $___________

3.In a step cost function where the steps are narrow, the cost behavior

                                           approaches the pattern of a:

                                           __________? cost

                                   

.

                                  4.(CPA) Adams Corporation developed the following budget for annual

indirect manufacturing labor cost:

                                    Total Cost = $4,800 + $0.50 (Machine-hours)

The operating budget for the current month is based on 20,000 machine-hours. Indirect manufacturing labor cost included in the monthly budget is:

$_________________.

5.(CMA) Ace Manufacturing Corporation found that the production of a certain product is subject to an 80% learning curve. The product is produced in lots of 100 units and 8 labor-hours are required for the first lot. Assuming Ace uses the cumulative average-time learning model, the total time required to produce 400 units is:

                                         _______________hours

                                   

                                   

                                        6.Using the information in question 5 and assuming Ace uses the            cumulative average-time learning model, the incremental time required to produce the second lot of 100 units is:

                                         ________________hours per unit

Explanation / Answer

Answer: 1 $4.00

The highest and lowest observations of DMLH are 3,650 and 2,050 respectively: ($19,800 – 13,400) / (3,650-2,050) = $6,40 / 1,600= $4 per hour

Answer:2 $5,200.

At the high point, $19,800 – 3,650(4) = $5,200

At the low point, $13,400 – 2,050(4) = $5,200

Answer:3 variable cost

Where the steps in a step cost function are narrow, the cost behavior approaches the pattern of a variable cost. In contrast, the steps are wide in a step fixed-cost function.

Answer:4 $10400

The key point is that the flexible-budget equation is for a Year, where as the flexible budget in the question is for a month. Therefore, $4,800/12= $400 per month; $400 + 20,000(0.50)= $10,400.

Answer:5 20.48 hours.

Answer:6 0.0480 hours per unit.

Using amounts from the computations in the preceding answer, 12.80 – 8.00= 4.80 hours; 4.80/ the second lot of 100 units = 0.0480 hours per unit.

Cumulative Number of Units Cumulative Average Hours per Unit Cumulative Total Hour 100 8.0 / 100= 0.08 100*0.0800= 8 200 0.0800 x 80% = 0.064 200 x 0.0640 = 12.8 400 0.0640 x 80% = 0.0512 400 x 0.0512 = 20.48