Wilkins Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations.Standard
Custom
Direct labor costs $55,200 $117,000 Machine hours 1,340 1,370 Setup hours 98 420Total estimated overhead costs are $298,600. Overhead cost allocated to the machining activity cost pool is $198,900, and $99,700 is allocated to the machine setup activity cost pool.
Explanation / Answer
Predetermined overhead rate = Estimated overhead /estimated direct labor cost
= 298,600 / (55200+117000)
= 298,600 / 172,200
= 1.7340 or 173.40%
b)
Machining 198,900 / (1340+1370) = 198900/2710 $ 73.39 per hour Machine set up 99700 /(98+420) = 99700/518 $ 192.47 per set upRelated Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.