Silmon Corporation makes a product with the following standard costs: In June th
ID: 2453089 • Letter: S
Question
Silmon Corporation makes a product with the following standard costs:
In June the company produced 4,300 units using 22,750 grams of the direct material and 2,590 direct labor-hours. During the month the company purchased 24,200 grams of the direct material at a price of $4.80 per gram. The actual direct labor rate was $12.60 per hour and the actual variable overhead rate was $1.90 per hour. The materials price variance is computed when materials are purchased. Variable overhead is applied on the basis of direct labor-hours.
Compute the following variances for raw materials, direct labor, and variable overhead, assuming that the price variance for materials is recognized at point of purchase: (Input all amounts as positive values. Do not round intermediate calculations. Leave no cells blank - be certain to enter "0" wherever required. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Omit the "$" sign in your response.)
Standard Quantityor Hours Standard Price
or Rate Direct materials 5.0 grams $ 5.00 per gram Direct labor 0.5 hours $ 12.00 per hour Variable overhead 0.5 hours $ 2.00 per hour
Explanation / Answer
Material Price variance
= (standard price – actual price) x actual quantity of material purchased
= ($5 - $4.80) x 24200
= $4840 Favourable
Material Quantity Variance
= (standard quantity for actual production – actual quantity used) x standard price
= (4300 units x 5gm per unit – 22750 gms) x $5/gms
= (21500 gms – 22750 gms) x $5 / gm
= $6250 Unfavourable
Labour Rate Variance
= (Standard rate – actual rate) x actual direct labour hours used.
= ($12 / hr - $12.60/hr) x 2590 hrs
= $1554 Unfavourable
Labour Efficiency variance
=(standard labour hours required for actual production – actual labour hour used) x standard rate
=(0.5 hrs/ unit x 4300 units – 2590 hours) x $12/hr
= $5280 Unfavourable
In absence of information, following variances have been calculated for Variable overhead
Variable overhead spending variance
= (standard overhead rate – actual overhead rate) x actual hours worked
= ($2 / hr - $1.90/hr) x 2590 hours
= $259 Favourable
Variable overhead efficiency variance
=( standard hours required for actual production – actual hours used) x standard overhead rate
= (0.5 hrs/ unit x 4300 units – 2590 hours) x $2/hr
= (2150 hrs – 2590 hrs) x $2 / hr
= $880 Unfavourable
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.