Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount
ID: 2453619 • Letter: M
Question
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:
Compute the throughput time. (Round your answer to 1 decimal place.)
Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.)
What percentage of the throughput time was spent in non–value-added activities? (Round your percentage answer to nearest whole percent.)
Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.)
If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate calculations. Round your answer to 2 decimal places.)
Inspection time 0.2 days Wait time (from order to start of production) 15.2 days Process time 3.1 days Move time 0.9 days Queue time 3.6 daysExplanation / Answer
Please find the calculations below
Part A: Throughput time = Process time + Inspection time + Move time + Queue time = 3.1 + .2 + .9 + 3.6 = 7.8
Part B: MCE = Value-added time (Process time)/ Throughput time = 3.1 days/ 7.8 days = 0.397
Part C: Percentage of time spent on non-value-added activities = 100% - MCE% = 100% - 39.7% = 60.003%
Part D: Delivery cycle time = Wait time + Throughput time = 15.2 days + 7.8 days = 23 days
Part E: Throughput time would change to: 4 days
MCE will become: 4/7.8 = .5128