6.
Manufacturing overhead is allocated to products based on the number of machine hours required. In a year when 20,000 machine hours were anticipated, costs were budgeted at $125,000. If a product requires 8,000 machine hours, how much manufacturing overhead will be allocated to this product?
A)
$41,667
B)
$31,120
C)
$43,750
D)
$50,000
6.
Manufacturing overhead is allocated to products based on the number of machine hours required. In a year when 20,000 machine hours were anticipated, costs were budgeted at $125,000. If a product requires 8,000 machine hours, how much manufacturing overhead will be allocated to this product?
A)
$41,667
B)
$31,120
C)
$43,750
D)
$50,000
Explanation / Answer
The correct answer is D) $ 50,000.
The budgeted machine hour rate is $ 125,000/ 20,000 hours = $ 6.25 per machine hour.
Therefore, if a product requires 8,000 machine hours, the manucturing overhead allocated to this product is $ 8000 x 6.25 = $ 50,000