Underfoot Products uses standard costing. The following information about overhe
ID: 2457023 • Letter: U
Question
Underfoot Products uses standard costing. The following information about overhead was generated during May:
Compute the variable overhead variance.
$21,000 (U)
$11,000 (F)
$1,000 (U)
$21,000 (F)
Standard unit costs generally do not include which of the following?
Indirect materials costs
Depreciation on machinery
Direct materials costs
President's salary
Standard variable overhead rate $2 per machine hour Standard fixed overhead rate $1 per machine hour Actual variable overhead costs $361,000 Actual fixed overhead costs $175,000 Budgeted fixed overhead costs $190,000 Standard machine hours per unit produced 10 Good units produced 18,000 Actual machine hours 200,000Explanation / Answer
CALCULATION OF VARIABLE OVERHEAD VARIANCE
VARIABLE OVERHEAD EFFICIENCY VARIANCE=Standard overhead rate x (Actual hours - standard hours)
=$2(2,00,000 HOURS-(10HOURS*18,000UNITS))
=$40,000 (U)
VARIABLE OVERHEAD SPENDING VARIANCE=Actual hours worked x (Actual overhead rate - standard overhead rate)
=2,00,000HOURS(($3,61,000/2,00,000HOURS)-$2)
=2,00,000HOURS($1.805-$2)
=$39,000 (F)
VARIABLE OVERHEAD VARIANCE=VARIABLE OVERHEAD EFFICIENCY VARIANCE+VARIABLE OVERHEAD SPENDING VARIANCE=$40,000(U)+( - $39,000(F))
=$1,000 (U)
HENCE c.$1,000(U) IS CORRECT
STANDARD UNIT COSTS GENERALLY DO NOT INCLUDE
d.PRESIDENT'S SALARY
UNIT COST IS THE COST INCURRED BY A COMPANY TO PRODUCE,STORE AND SELL ONE UNIT OF A PARTICULAR PRODUCT .UNIT COSTS INCLUDE ALL FIXED COSTS(I.E PLANT AND EQUIPMENT) AND ALL VARIABLE COSTS (I.E LABOUR,MATERIALS,ETC.) INVOLVED IN PRODUCTION.PRESIDENT'S SALARY IS
NOT A COST INVOLVED IN PRODUCTION.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.