Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Use the following to answer question 28: Horner Construction Co. uses the percen

ID: 2459627 • Letter: U

Question

Use the following to answer question 28:

Horner Construction Co. uses the percentage-of-completion method. In 2010, Horner began work on a contract for $5,500,000; it was completed in 2011. The following cost data pertain to this contract:

     Year Ended December 31

    

2010

   2011

Cost incurred during the year

$1,950,000

$1,400,000

Estimated costs to complete at the end of year

1,300,000

        —

      28. The amount of gross profit to be recognized on the income statement for the year ended December 31, 2011 is ?

     Year Ended December 31

    

2010

   2011

Cost incurred during the year

$1,950,000

$1,400,000

Estimated costs to complete at the end of year

1,300,000

        —

Explanation / Answer

In $ Contract Price 5500000 Construction cost 3350000 Gross Profit 2150000 Gross Profit ratio 39% Percentage of Complete Gross profit Year Cost Incurred Percentage of completion Revenue to be recognised Gross Profit 2010                                  19,50,000 58.21%                                  32,01,493                                 12,48,582 2011                                  14,00,000 41.79%                                  22,98,507                                   8,96,418                                  33,50,000 100.00%                                  55,00,000                                 21,45,000 The gross profit to be recognised on the income statement for the year ended December 31,2011 is $8,96,418.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote