Below are standard and actual labor data for the current month for Zellner Compa

ID: 2459946 • Letter: B

Question

Below are standard and actual labor data for the current month for Zellner Company.The company produced 1,000 units

Standard direct labor cost per unit

2 hours at $15.00 per hour

Actual data for current month

Employees worked 1,800 hours at $16.00 per hour



The labor rate variance is:

Below are standard and actual labor data for the current month for Zellner Company.The company produced 1,000 units

Standard direct labor cost per unit

2 hours at $15.00 per hour

Actual data for current month

Employees worked 1,800 hours at $16.00 per hour



The labor rate variance is:

Explanation / Answer

SRSH                                              SRAH                                                               ARAH

      2000 x 15                                                  1800 x 15                                                        1800 x 16

         =30,000                                                  = 27,000                                                           = 28,800

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     

SR = Standard Rate = $ 15

SH = Standard Hours for Actual Production = 1000 x 2 =2,000

AH = Actual Hours = 1800

AR = Actual Rate =16

Labour Rate Variance = SRAH – ARAH = 27,000 – 28,800

= -1,800   [U]