Question 1 (a) Question 1 Daisy Construction Ltd. has entered into a contract be
ID: 2461049 • Letter: Q
Question
Question 1
(a)
Question 1
Daisy Construction Ltd. has entered into a contract beginning January 1, 2014, to build a parking complex. It has estimated that the complex will cost $8 million and will take three years to construct.The complex will be billed to the purchasing company at $11.5 million. The details are as follows:
2014 2015 2016 Costs to date $ 3,060,000 $ 6,435,000 $ 8,600,000 Estimated costs to complete 4,595,900 1,964,375 –0– Progress billings to date 4,000,900 6,300,000 11,500,000 Cash collected to date 3,500,900 5,000,000 11,500,000
Under the earnings approach:
Explanation / Answer
Gross profit to date = % complete X Total estimated gross profit
Total Estimated Gross profit =Total Contract Amount-Total Cost
=$11,500,000-$8,600,000
=$2,900,000
% of Work complete :
2014:
=cost incurred to date/( cost incurred to date+ Estimated cost to complete)
=$3,060,000/($3,060,000+$4,595,900)
=$3,060,000/$7,655,900=39.97%
Gross Profit 2014=$2,900,000 x 39.97%=$1,159,130
% of Work complete :
2015:
=cost incurred to date/( cost incurred to date+ Estimated cost to complete)
=$6,435,000/($6,435,000+$1,964,375)
=$6,435,000/$8,399,375=72%
Gross Profit 2014=$2,900,000 x72%=$2,088,000
Current year's gross profit = Gross profit to date - Gross profit in prior years
=$2,088,000-$1,159,130
=$928,870
2016: Gross profit = Total Gross Profit-Gross profit till previous years
=$2,900,000-$2,088,000=$812,000
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.