Quick Silver Company has two departments, X and Y. Overhead is applied based on
ID: 2461228 • Letter: Q
Question
Quick Silver Company has two departments, X and Y. Overhead is applied based on direct labor cost in Department X and machine-hours in Department Y. The following additional information is available: Budgeted Amounts Department X Department Y Direct labor cost $180,000 $165,000 Factory overhead $225,000 $200,000 Machine-hours 51,000 mh 40,000 mh Actual data for Job #25 Department X Department Y Direct materials requisitioned $15,000 $18,000 Direct labor cost $11,000 $14,000 Machine-hours 5,000 mh 3,000 mh Required: a. Compute the budgeted factory overhead rate for Department X. 225,000/180,000 = 1.25 or 125% b. Compute the budgeted factory overhead rate for Department Y. 200,000/40,000 = $5 per machine- hour c. What is the total overhead cost of Job 25?
Explanation / Answer
Solution:
a. Department X
Budgeted factory overhead rate = Factory overhead/Direct labor cost
Budgeted factory overhead rate = $225,000/$180,000
Budgeted factory overhead rate = 1.25 or 125%
b. Department Y
Budgeted factory overhead rate = Factory overhead/Machine hours
Budgeted factory overhead rate = $200,000/40,000
Budgeted factory overhead rate = $5 per machine hour
c. Total overhead cost for Job 25 = $11,000 x 1.25 + 5 x 3,000
Total overhead cost for Job 25 = $28,750