Assume that General Dynamics, which manufactures high-technology instruments for
ID: 2462173 • Letter: A
Question
Assume that General Dynamics, which manufactures high-technology instruments for spacecraft, is considering the sale of a navigational unit to a government agency in India that wishes to launch its own communications satellite. The government agency plans to purchase 8 units, although it would also consider buying 16 units. General Dynamics has started a chart relating labor time required to units produced. Required: Complete the labor time required to produce 8 and 16 units. (Round your answers to 2 decimal places (i.e., 32.21))Explanation / Answer
learning % = 16800/24000 *100 = 70%
or 11760/16800 = 70%
In order to calculate time required for 8th unit, we should apply mathematical formula
Y = axb
Y = 24000 * (8)-0.1549
log Y = log 24000 + log(8)-0.1549
log Y = log24000 - 0.1549 * log 8
log y = 0.3802 - 0.1549*0.90309
log y = 0.240311
anti log y = anti log 0.240311
y = 1270.6
Time required to produce the 8 units = 8*1270.6 = 10165 hours
Time required to produce the 16 units = 11760 * 70% = 8232 hours
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.