Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

9. Ex.10-28 Budget Variances, Materials and Labor Cinturon Corporation produces

ID: 2464615 • Letter: 9

Question

9. Ex.10-28

Budget Variances, Materials and Labor
Cinturon Corporation produces high­quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor:

eBook

Leather (3 strips @ $4) Direct labor (0.75 hr. @ $12) Total prime cost

$12.00 9.00 $21.00

During the first month of the year, Boise plant produced 92,000 belts. Actual leather purchased was 287,500 strips at $3.60 per strip. There were no beginning or ending inventories of leather. Actual direct labor was 78,200 hours at $12.50 per hour.

Required:
1.
Compute the costs of leather and direct labor that should be incurred for the production of 92,000 leather belts.

Cost of materials $ Cost of direct labor $

2. Compute the total budget variances for materials and labor. Total Budget Variance

Materials $ Labor $

3. Conceptual Connection: Would you consider these variances material with a need for investigation?

Explanation / Answer

For output of 92,000 belts, as per standards, material & direct labour should have been used as follows.

Standard Quantity (SQ) = 3 strips x 92,000 = 276,000 strips

Standard Direct labour (SDL) = 0.75 hr x 92,000 = 69,000 hrs.

Answer to question 1:

costs of leather and direct labor that should be incurred for the production of 92,000 leather belts

a) Cost of leather : SQ x Standard Rate(SR) = 276,000 strips x $4 = $1,104,000

b) Cost of direct labour: Std. Cirectlabour Hrs. x SR = 69,000 x $12 = $ 828,000

Total Prime Cost = a+b = $1,932,000

Answer to question No.2: Total budget variances for materials and labor

Material Cost Variance : SQ x SR - AQ x AP = (276000 x 4) - ( 287500 x 3.60)

   = $1,104000 - $1,035,000 = $69,000 (Favorable)

Direct Labour Cost Variance = Standard Wages - Actual Wages

= (Std. Hr x SR) - (Actual Hr x AR)

= (69,000 hr x $12.00) - ( 78,200 hr x $12.50)

= $828,000 - 977,500 = $149,500 (Unfavourable)

Answer to question No.3:

Yes. Both teh variances needs to be investigated.

Material: Though matrial per strip actual variance is lesser than SR, but its usage is below standards. Hence mnaterial usage can be investigated.

Direct Labour: Hour usage & rate both are higher than the standard set. Hence both needs to be investigated. .