Standard Custom (a) Wilkins Inc. has two types of handbags: standard and custom.
ID: 2466692 • Letter: S
Question
Standard
Custom
(a)
Wilkins Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations.Standard
Custom
Direct labor costs $44,800 $119,000 Machine hours 1,470 1,240 Setup hours 110 400Total estimated overhead costs are $301,100. Overhead cost allocated to the machining activity cost pool is $195,300, and $105,800 is allocated to the machine setup activity cost pool.
Explanation / Answer
Total Direct Labour cost = $44800 + $119000 = $163800 Standard Predermined overhead rate = (Direct labour cost of Standard / Total direct labour cost)*100 Standard Predermined overhead rate = (44800 / 163800)*100 = 27.35% of direct labour cost Custom Predermined overhead rate = (Direct labour cost of Custom / Total direct labour cost)*100 Custom Predermined overhead rate = (119000 / 163800)*100 = 72.65% of direct labour cost
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.