Fletcher Company collected the following data regarding production of one of its
ID: 2467150 • Letter: F
Question
Fletcher Company collected the following data regarding production of one of its products. Compute the fixed overhead cost variance.
Direct labor standard (2 hrs. @ $12.75/hr.) $25.50 per finished unit
Actual direct labor hours 81,500 hrs. Budgeted units 42,000 units
Actual finished units produced 40,000 units Standard variable OH rate (2 hrs. @ $14.30/hr.) $28.60 per finished unit
Standard fixed OH rate ($336,000/42,000 units) $8.00 per unit
Actual cost of variable overhead costs incurred $1,140,000
Actual cost of fixed overhead costs incurred $338,000
Explanation / Answer
Fixed overhead cost variance.
1.Fixed overhead spending variance= Budgeted fixed overhead cost- Actual fixed overhead incurred
=$336,000-$338,000
=(2,000) (U)
2.Fixed overhead volume variance
=(Budgeted fixed overhead/budgeted production * units produced) -Budgeted fixed overhead
=($336,000/42000units*40000 units) -$336,000
=$320,000-$336,000
=$16,000(U)
Total fixed overhead cost variance =Fixed overhead spending variance+Fixed overhead volume variance
=($2,000) (U)+($16,000)(U)
=($18,000)(U)
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.