Antuan Company set the following standard costs for one unit of Its product Dire
ID: 2470050 • Letter: A
Question
Antuan Company set the following standard costs for one unit of Its product Direct materla's (3.0 lbs. $4.0 per lb.) Direct labor (2.0 hrs. $12.0 per hr) Overhead (2.0 hrs. $18.50 per hr.) $ 12.00 24.00 37.00 Total standard cost $ 73.00 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the 75% level. Overhead Budget (75% Capacity) Variable overhead costs Ind rect materia's Ind rect labor Power Repairs and maintenance $ 15,000 75,000 15,000 45,000 Total variable overhead costs $150,000 Fixed overhead costs 23,000 74,000 7,000 291,000 Taxes and insurance Total fixed overhead costs 405,000 Total overhead costs $555,000 The company incurred the following actual costs when it operated at 75% of capacity in October. Direct materla's (46,000 lbs. $4.10 per Ib.) Direct labor (29,000 hrs. $12.40 per hr) Overhead costs $ 188,600 359,600 $ 45.750 177,250 17,250 51,750 23,000 99,900 Ind rect materla's Ind rect labor Repairs and maintenance Taxes and insurance 291,000 721,200 Total costs $1,269,400Explanation / Answer
Direct Labour Cost Data
2x15000
= 30000
Direct Labour Rate Variance = (Standard Rate - Actual Rate) x Actual Hours
= (12-12.4)x 29000
= $11600 Unfavourable
Direct Labour Efficiency Variance = (Standard Hours - Actual Hours) x Standard Rate
= (30000-29000) x 12
= $12000 Favourable
Direct Labour Cost Variance = -11600+ 12000
= $400 Favourable
Standard Hours Standard Rate Standard Cost Actual Hours Actual Rate Actual Cost Direct Labour2x15000
= 30000
12 360000 29000 12.4 359600Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.