Question
Determining Cost of Land
Fastball Delivery Company acquired an adjacent lot to construct a new warehouse, paying $28,000 and giving a short-term note for $287,000. Legal fees paid were $1,470, delinquent taxes assumed were $13,800, and fees paid to remove an old building from the land were $17,200. Materials salvaged from the demolition of the building were sold for $4,700. A contractor was paid $957,600 to construct a new warehouse.
Determine the cost of the land to be reported on the balance sheet.
$
Explanation / Answer
Calculation of Cost of Land $ Initial payment 28,000 Short-term note 2,87,000 Legal fees 1,470 Fees to remove old building 17,200 Material salvaged from demolition of building -4,700 Construction cost to contractor 9,57,600 Cost of Land 12,86,570