Niemiec Corporation keeps careful track of the time required to fill orders. The

ID: 2473946 • Letter: N

Question

Niemiec Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below:

The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculation and final answer to 2 decimal places.)

0.03

0.17

0.93

0.09

Aide Industries is a division of a major corporation. Data concerning the most recent year appears below:



The division's return on investment (ROI) is closest to: (Round your answer to 2 decimal places.)

2.20%

5.20%

19.55%

15.70%

Niemiec Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below:

Explanation / Answer

The manufacturing cycle efficiency (MCE):

MCE = Value-added time / Throughput time

=1.4/16=0.0875

Value-added time=Process time=1.4

throught put time=move time+Queue time+process time+Inspection time =1.7+12.6+1.4+0.3=16