Activity Based Costing: Vid-saver, Inc. has five activity cost pools and two pro
ID: 2476131 • Letter: A
Question
Activity Based Costing:
Vid-saver, Inc. has five activity cost pools and two products (a budget tape rewinder and a deluxe tape rewinder). Information is presented below:
Cost Drivers by Product
Activity Cost Pool Cost Driver Est. Overhead Budget Deluxe
Ordering and Receiving Orders $ 110,000 600 400
Machine Setup Setups 297,000 500 400
Machining Machine hours 1,000,000 150,000 100,000
Assembly Parts 1,200,000 1,200,000 800,000
Inspection Inspections 300,000 550 450
Instructions
Compute the overhead cost per unit for each product. Production is 700,000 units of Budget and 200,000 units of Deluxe. Round your answer to the nearest cent. -Make sure to show how you got the answer.
Explanation / Answer
Ans) Vid-saver, Inc. Activity cost Tool Est.Overhead/Total Est.Activity Overhead Rate Overhead Rate Ordering & receiving $ 110,000.00 1000 Orders $ 110.00 Machine setup $ 297,000.00 900 Setups $ 330.00 Machining $ 1,000,000.00 250000 Machine Hours $ 4.00 Assembly $ 1,200,000.00 2000000 Parts $ 0.60 Inspection $ 300,000.00 1000 Inspections $ 300.00 Budget Activity cost Tool Cost Driver Rate Cost Assigned Ordering & receiving 600 $ 110.00 $ 66,000.00 Machine setup 500 $ 330.00 $ 165,000.00 Machining 150000 $ 4.00 $ 600,000.00 Assembly 1200000 $ 0.60 $ 720,000.00 Inspection 550 $ 300.00 $ 165,000.00 Total $ 1,716,000.00 Production 700000 Cost Per unit $ 2.45 Per unit Deluxe Activity cost Tool Cost Driver Rate Cost Assigned Ordering & receiving 400 $ 110.00 $ 44,000.00 Machine setup 400 $ 330.00 $ 132,000.00 Machining 100000 $ 4.00 $ 400,000.00 Assembly 800000 $ 0.60 $ 480,000.00 Inspection 450 $ 300.00 $ 135,000.00 Total $ 1,191,000.00 Production 200000 Cost Per unit $ 5.96 Per unit