Question

#22

The following materials standards have been established for a particular product:

  Standard quantity per unit of output

8.4

meters

  Standard price

$14.05

per meter

  

The following data pertain to operations concerning the product for the last month:

  Actual materials purchased

6,000

meters

  Actual cost of materials purchased

$72,000

  Actual materials used in production

5,800

meters

  Actual output

560

units

What is the materials price variance for the month?

a. $18,080 U

b. $13,152 U

c. $2,400 U

d. $12,300 F

  Standard quantity per unit of output

8.4

meters

  Standard price

$14.05

per meter

Explanation / Answer

Calculation of materials price variance:

Materials price variance = (Actual Price – Standard Price )*Actual Quantity

Actual Price = Actual cost of materials purchased / Actual materials purchased

= $72000 / 6000 Meters

= $12 Per Meter

Standard price = $14.05 Per Meter

Actual Quantity = Actual materials Purchased = 6000 Meters

Hence,

Materials price variance = (12 – 14.05 )*6000 =12300 Favorable